Solar Roof Top Power Project

Dalhousie Public School

  • START: AUG 2018
  • COMPLETION: DEC 2018
  • Capacity: 265 kW
  • Total value of Work Order (INR): 02 Cr

Govt. ITI, Nehran Pukhar

  • START: NOV 2019
  • COMPLETION: DEC 2019
  • Capacity: 35 kW
  • Total value of Work Order (INR): 0.18 Cr

VVM Nursing College Nurpur

  • START: NOV 2019
  • COMPLETION: DEC 2019
  • Capacity: 50 kW
  • Total value of Work Order (INR): 0.25 Cr

Thakur Pre Siksha Traning & Coaching Centre (Dehra)

  • START: OCT 2019
  • COMPLETION: DEC 2019
  • Capacity: 98 kW
  • Total value of Work Order (INR): 0.76 Cr

Govt. ITI Bangana Distt. Una

  • START: JULY 2022
  • COMPLETION: JULY 2022
  • Capacity: 41 kW
  • Total value of Work Order (INR): 0.19 Cr

Govt. Degree Collage Dhaliara

  • START: OCT 2019
  • COMPLETION: NOV 201P
  • Capacity: 33 kW
  • Total value of Work Order (INR): 0.17 Cr

Govt Degree Collage Chamba

  • START: SEPT 2019
  • COMPLETION: OCT 2019
  • Capacity: 25 kW
  • Total value of Work Order (INR): 0.13 Cr

Ground Mounted Solar Power Projects

Lucky Brass Solar PV Project

  • Capacity: 2.0 MW
  • Location Una

K_Solr Power Project, Fatehpur

  • Capacity: 0.5 MW
  • Location Jawali, District Kangra

Kartik Solar Power Project, Fatehpur

  • Capacity: 1.0 MW
  • Location Jawali, District Kangra

Kushal Solar Power Project, Fatehpur

  • Capacity: 1.0 MW
  • Location Jawali, District Kangra

Ankur Solar Power Project, Fatehpur

  • Capacity: 1.0 MW
  • Location Jawali, District Kangra

Ankit Solar Power Project, Fatehpur

  • Capacity: 1.0 MW
  • Location Jawali, District Kangra

Small Hydro Projects

Brahl Top Small Hydro Projects

  • Capacity: 5.0 MW
  • Location Brahl

Leond Nouli Small Hydro Project

  • Capacity: 4.0 MW
  • Location Leond Nouli

Gajeu Ghera Small Hydro Project

  • Capacity: 2.50 MW
  • Location Gajeu Ghera